Strip out & skip
£800 labour + £250 skip
£
£1,050
Rewire (electrics)
× 85 m² = £8,500
£
£8,500
Plaster walls & ceilings
× 85 m² = £2,550
£
£2,550
Decorating / wall finishes
× 85 m² = £1,700
£
£1,700
Flooring
× 85 m² = £3,400
£
£3,400
New internal doors
£350 each (£150 door + £200 fit) = £2,100
doors
£2,100
New bathroom(s)
£2,000 materials + 6 days labour = £3,800
no.
£3,800
New kitchen
£1,500 materials + 5 days labour = £3,000
no.
£3,000
New en-suite
£10,000 per unit = £0
no.
£0
Replace radiators
£200 each = £600
rads
£600
Smoke & heat alarms
mains-wired, interlinked
£
£350
Windows
£1,000 each = £3,000
no.
£3,000
Damp assessment & rectify
£2,000 per area = £0
areas
£0
Certificates
£500 each (EICR, gas, EPC, etc.) = £0
certs
£0
Extension
£2,000 per m² = £0
£0
Fireplace
around £200
£
£200
New partition wall
stud wall (if reconfiguring)
£
£1,000
Roof (re-roof)
typical £7.5k–£15k for a 3-bed
£
£9,000
Boiler / central heating
new boiler + heating works
£
£4,000
Driveway
block paving ~£90–£130/m²
£
£4,000
Patio
~£90–£140/m²
£
£2,500
Garden / landscaping
medium garden ~£3,000–£6,000
£
£3,000
Miscellaneous
anything else — enter a cost
£
£0

Estimated refurb cost

£28,710
incl. 10% contingency · £338/m²
Works subtotal£26,100
Contingency (10%)£2,610
Total refurb budget£28,710
Cost per m²£338/m²
Regional rates are indicative. Pair this with the Property Value Estimator for the GDV, then run the BRR calculator.
Get a PDF of this refurbishment cost estimator

Your results are right here on the page — free, no sign-up. Add your name and email and we’ll open a clean, printable PDF of this page (choose “Save as PDF”).

How the estimate is built

Each line is priced one of three ways: a fixed cost (boiler, roof), a per-unit cost where you enter a quantity (doors, bathrooms, en-suites, certificates), or a per-square-metre rate applied to your floor area (rewiring £100/m², plastering £30/m², decorating £20/m², flooring £40/m²). Bathrooms and kitchens add labour at a day rate you set. Add a contingency (10% is standard) for the surprises every refurb throws up.

  • Strip out and skip, rewire, plastering, internal doors, kitchen, bathroom, decorating and flooring are on by default.
  • Optional extras - en-suite, radiators, smoke & heat alarms, damp rectification, certificates, roof, extension, fireplace, partition wall, boiler, windows, driveway, patio, garden and a miscellaneous line - are off until you tick them.
  • Every figure is editable: defaults reflect typical UK buy-to-let refurb pricing, which is leaner than retail-quote averages.
  • The result shows the works subtotal, the contingency, the total budget and the cost per square metre as a sanity check.

Worked example - light/medium refurb of a 3-bed

Strip out £1,050; rewire £4,000; plaster 6 rooms x £300 = £1,800; 6 doors x £50 = £300.

Bathroom £1,000 + 5 days = £2,500; kitchen £1,500 + 5 days = £3,000; decorating £2/m² x 85 + 6 days = £1,970; flooring £1,250.

Subtotal about £15,870; add 10% contingency (£1,587) = about £17,460 (roughly £205/m²).

External works (current UK guide prices)

  • Driveway (block paving): about £90–£130 per m² installed.
  • Patio: about £90–£140 per m² installed.
  • Garden / landscaping: a medium garden typically £3,000–£6,000.
  • New combi boiler installed: UK average around £2,400 (£1,800–£4,500 depending on system).

Treat the total as a planning budget, not a quote. Always get builder quotes for the actual job, and keep the contingency - older properties hide damp, wiring and structural surprises.

Frequently asked questions

Why are your defaults lower than the prices I see online?
Retail cost guides quote homeowner prices. Experienced investors refurbishing a buy-to-let buy materials keenly and use trade labour, so a BTL refurb is usually cheaper per item. The defaults here reflect that - and every line is editable if your job is higher spec.
What contingency should I use?
10% is the common rule of thumb for a standard refurb. For older or unknown-condition properties, or a heavy refurb, 15–20% is safer.
Does this include an extension?
Yes - there is an optional extension line at a £2,000/m² base rate; enter the extension size and it is added automatically. Treat it as a planning-stage ballpark and confirm with a builder; price complex structural work or loft conversions separately.
How does this connect to the BRR and GDV tools?
The refurb total feeds the 'refurb budget' in the BRR calculator, and the Property Value Estimator gives you the GDV. Use the buttons to carry the figures across so the three tools work as one deal appraisal.

Related calculators

Important: BrickCrunch provides general information and estimates only — this is not financial, tax, mortgage or legal advice. Calculations are simplified and your circumstances may differ. UK tax and rate figures are checked against gov.uk (21 June 2026 (2026/27 tax year)) but rates change and errors are possible. Always confirm figures with gov.uk or a qualified professional before making decisions.